Regular MeetingJune 12, 2026 | 9:30 a.m. Location: Green Line Extension Project Office - 6465 Wayzata Blvd., St. Louis Park, MN 55426 (5th Floor)
Approval of the use of project contingency in the amount of $14,571,036.67 for Change Order 181 to the Systems Tunnel Facilities Contract with Aldridge – Parsons, a Joint Venture, for claims resolution costs associated with an extension of time to the contract, and for Systems maintenance activities.
Approval of the use of project contingency in the amount of $1,759,180.03 for Change Order 175 to the Systems and Tunnel Facilities (STF) Contract with Aldridge Parsons, a Joint Venture (APJV) to construct the systems elements of the Hopkins pocket track.
Approval of the use of project contingency in the amount of $420,000 for Change Order 170 to the Systems and Tunnel Facilities (STF) Contract with Aldridge Parsons, a Joint Venture (APJV) to furnish and install cameras, emergency telephones, card readers, and associated cabling in the Beltline Boulevard Station parking ramp.
Green Line Extension Executive Change Control Board