Green Line Extension Executive Change Control Board Meeting

Regular Meeting
September 13, 2024 | 11:00 a.m.
Location: Green Line Extension Project Office - 6465 Wayzata Blvd., St. Louis Park, MN 55426 (5th Floor)
Minutes (PDF)

For in-person meetings held at the Robert Street location: As of 1/20/26, to enter the building, simply press the call button located at the west side doors (nearest Robert Street). Our front desk team will be promptly alerted and will assist you with entry.

Agenda

1.     Welcome 

2.     Minutes from August 9, 2024

3.     Resolution 24-ECCB-017

·       Approval of the use of Project Contingency in the amount of $731,729.74 for Change Order 1037 to the Civil Construction Contract for the modification of the Kenilworth Tunnel secant pile wall alignment and tunnel wall thickness.

4.     Resolution 24-ECCB-018

·       Approval of the use of Project Contingency in the amount of $366,979.17 for Change Order 0954 Contract to provide 24-hour freight rail monitoring on the Cedar Lake Spur due to construction activities associated with the Kenilworth Tunnel (27C15).

5.     Monthly Report on Change Orders  

Adjourn